| | Posted by ha_tran (Senior SAP Supply Chain Business Analyst) on Feb 2 at 7:06 PM | |
Hi,
Just a brief clarification that you can't change the statistic delivery date once the PO is transmitted to the vendor. It is only the delivery date (via either vendor confirmation entry or manually in the PO item overview) that you can change in ME22N transaction.
Cheers,
HT
---------------Original Message---------------
From: Denise Michaels
Sent: Tuesday, February 02, 2010 3:27 PM
Subject: Statistics-relevant delivery date/delivery date
> The statistics relevant date is used for the purposes of MRP.? The delivery date is the date agreed upon by the vendor to deliver and is used for vendor evaluation to score delivery date performance.<br/>Having two dates allows the purchasing person to show that the delivery is later than promised and have the new date be MRP relevant, but still save the original promised date to score the vendor against.<br/>So when a vendor needs to slip a date, the purchasing person usually changes only the stat date and leaves the delivery date.<br/>If the purchasing person asks for? a different date which is agreed to by the vendor, he/she changes both dates.
__.____._ Just a brief clarification that you can't change the statistic delivery date once the PO is transmitted to the vendor. It is only the delivery date (via either vendor confirmation entry or manually in the PO item overview) that you can change in ME22N transaction.
Cheers,
HT
---------------Original Message---------------
From: Denise Michaels
Sent: Tuesday, February 02, 2010 3:27 PM
Subject: Statistics-relevant delivery date/delivery date
> The statistics relevant date is used for the purposes of MRP.? The delivery date is the date agreed upon by the vendor to deliver and is used for vendor evaluation to score delivery date performance.<br/>Having two dates allows the purchasing person to show that the delivery is later than promised and have the new date be MRP relevant, but still save the original promised date to score the vendor against.<br/>So when a vendor needs to slip a date, the purchasing person usually changes only the stat date and leaves the delivery date.<br/>If the purchasing person asks for? a different date which is agreed to by the vendor, he/she changes both dates.
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
White Papers
In the Spotlight
Share Knowledge About SAP Scripting. Join the New Discussion Group
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion