RE:[sap-log-pp] Limit the conversion of planned order into production in a certain horizon
Posted by
Admin at
|
Share this post:
|
0 Comments
| | Posted by christophe-carmaux on Jan 27 at 3:01 PM | |
None of these proposals can be used in my case :
- raw materials requirements (long term) are generated by upper level materials (short production cycle). So I cannot play with MRP runs
- Orders must be released immediately.
There were good suggestions, but ... not applicable taking existing constraints into consideration.
Thanks
Christophe
---------------Original Message---------------
From: christophe-carmaux
Sent: Wednesday, January 27, 2010 11:16 AM
Subject: Limit the conversion of planned order into production in a certain horizon
> Hi, <br/>We are requested by the production department to restrict the timeframe in which people can convert the planned orders into production orders.<br/>We cannot restrict the MRP horizon, as we need to keep the visibility of row materials (pruchasing cycle is very long).<br/>So we need to keep all planned orders but restrict the autorisation for users to convert them into production orders into a limited timeframe.<br/>Is there a standard way to deal with such requests ?<br/>Thanks for your advises.<br/>Regards
__.____._ - raw materials requirements (long term) are generated by upper level materials (short production cycle). So I cannot play with MRP runs
- Orders must be released immediately.
There were good suggestions, but ... not applicable taking existing constraints into consideration.
Thanks
Christophe
---------------Original Message---------------
From: christophe-carmaux
Sent: Wednesday, January 27, 2010 11:16 AM
Subject: Limit the conversion of planned order into production in a certain horizon
> Hi, <br/>We are requested by the production department to restrict the timeframe in which people can convert the planned orders into production orders.<br/>We cannot restrict the MRP horizon, as we need to keep the visibility of row materials (pruchasing cycle is very long).<br/>So we need to keep all planned orders but restrict the autorisation for users to convert them into production orders into a limited timeframe.<br/>Is there a standard way to deal with such requests ?<br/>Thanks for your advises.<br/>Regards
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
White Papers
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion