Question from levo007 on May 18 at 6:16 AM Hello, Does anyone know how to determine Progress % considering exclusion of certain cost elements from % determination? Example: Plan Actual CE1 100 50 CE2 700 150 CE3 100 20 ==================== Total 900 220 Requirement is to include only CE 1 & CE 2 into POC% determination. So progress should be = (50+150) / (100+700) = 200 / 800 = 25%; Normally system include all CE to Progress determination. I've tried to resolve it with 2 progress technical CE (type 61), but system still returns full value. I use Cost proportional measurement method. Any help is appreciated. Thank you, M | Reply to this email to post your response. __.____._ | _.____.__ |