Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Question from Wasim2921 on Apr 26 at 6:45 PM Hello friends and respected sir, I have a scenario, I am working for a real state company there we have a MEP vendor for that we have created a service PO for submitting the various drawing (eg plumbing, electrical and mechanical load drawing ) by this he needs to submit us a total of 5 drawings but so far he has submitted only two, so is there a scenario where we could pay for the completed services only and for remaining services i could raise a Service Po to another vendor ? How would I map in to sap ? Please explain Thanks Wasim | Reply to this email to post your response. __.____._ | _.____.__ |