Reply from tomevans866 on Dec 30 at 10:41 AM
Jeff,
I think you will need to write another LSMW to make the changes on the Maint. Items.
SAP allows different Planner Groups on the Maint Items (and Work Orders). I have used this flexibility to group work to different planners for the same equipment.
Thus, while it defaults when creating a Maint. Item, it would not inherit a change.
Tom

---------------Original Message---------------
From: Jeff
Sent: Monday, December 07, 2015 4:21 PM
Subject: Updates to maintenance items due to change in Floc

We have used the Planner Group to associate to the person responsible for a Floc. There is a large number of existing Floc's (+9,000).

We now have to redistribute a large number of these Floc's from one planner group to another. We will most likely use an LSMW to achieve that change.

During some testing we found that even though we updated the planner group of the Floc the change does not filter through to change the individual maintenance items that have been set up for that Floc.

Does anyone know of a way to initiate an inheritance that could possibly update the maintenance items. This would save a lot of manual updates!

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
© 2015 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
tomevans866  

Consultant
achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language