Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Reply from SAPAUSSEC on Oct 27 at 5:07 AM The short answer you can only delete WBS elements, activities if they have the status created and no postings or other assignments exist To delete a project is not recommended or possible unless a function module is used and this is bypassing SAP controls. The correct approach is to go through an archive process to remove a project and its data in the correct sequence. Any other method will cause data inconsistencies and errors.
| | | ---------------Original Message--------------- From: Dikshita Sent: Tuesday, October 27, 2015 3:47 AM Subject: How Can a Project Be Deleted Is there any other T-Code to delete project with further procedures? | | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |