Reply from kjclark on Jul 27 at 1:03 PM Changing the Factory Calendar is not viewed as a viable option for getting a truer valuation of the Breakdown Duration. Scheduling the work is the Key factor along with assigning the work to the correct Work Center. The recommended method is to Set up Intervals and Shifts at the Work Center Level/s and if you are really interested you can use Prometheus Solutions and schedule the individual workers by person.. Confirmation of time is also critical. Time must be confirmed by date and time and finalized only when the work is actually completed.
| | | ---------------Original Message--------------- From: Tmcginn Sent: Friday, July 24, 2015 11:05 AM Subject: Where To Set A Factory Calendar For The Breakdown Duration? Where can I set a factory calendar for the breakdown duration? I don't want the the breakdown duration to count non working days? | | Reply to this email to post your response. __.____._ | _.____.__ |