Reply from rsvrmurthy on Jul 18 at 4:09 PM Hi, Thank you Akula. It's not displaying actual hours though selected particularly that WBSE or Project definition. Regards, Murthy.
| | | ---------------Original Message--------------- From: David Tsimerman Sent: Friday, July 17, 2015 8:22 AM Subject: Actual Hours Not Reflecting In CNS41 Report If CN48N shows the actual Hours, then CNS41 will show the same unless WBS Level is not selected correctly (leave default 1 to 99) or Origin of Data is not "Current" Thanks, Akula | | Reply to this email to post your response. __.____._ | _.____.__ |