Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Reply from Acula on Jul 17 at 8:09 AM If CN48N shows the actual Hours, then CNS41 will show the same unless WBS Level is not selected correctly (leave default 1 to 99) or Origin of Data is not "Current" Thanks, Akula
| | | ---------------Original Message--------------- From: RSVR Murthy Sent: Friday, July 17, 2015 1:56 AM Subject: Actual Hours Not Reflecting In CNS41 Report Hi, Thank you for your response. I checked that report and it's showing actual hours but user wants the reason why it's not reflecting in CNS41 report. Regards, Murthy. | | Reply to this email to post your response. __.____._ | _.____.__ |