RE:[sap-log-pm] Extending Maint Plan Timescale for Completion

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from pauljb470 on May 6 at 12:34 AM
It can be done, but is dependent on a few things
I will use a simple example which you can adjust according to your task lists complexity
1 operation 4 hours work
in the operation of the task list select the manually maintain calculation key. Enter the work of 4 hours, but enter a duration of 56.
My work centres are based on 8 hours capacity so it will have a 7 day difference between start and finish.

I think factory calendar may come into play , but this depends how you are set up.

You should be able to work it out through trial and error for your specific work centres, and will work for multi operation task lists.

---------------Original Message---------------
From: Aldered
Sent: Saturday, April 25, 2015 3:47 PM
Subject: Extending Maint Plan Timescale for Completion

My maintenance plans are set to come out on a Sunday but the end date is also the Sunday.
How do I make the end day a week later or 2 weeks later etc.
Essentially giving me longer to complete the plan.

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2015 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
pauljb470  

achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language