Re: [sap-log-ps] What do I need to change in order to do a complete settlement of an asset?

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from lokeshsethi on Mar 31 at 11:36 AM
There are two ways to resolve this issue:
1. 1st and most logical way is to maintain the cost element in the cost
element group used in allocation structure Y3 and carry out settlement.
2. 2nd way is to reverse the posting made to WBS and carry out settlement
(not recommended)

Regards
Lokesh Sethi

---------------Original Message---------------
From: RSVR Murthy
Sent: Tuesday, March 31, 2015 1:20 AM
Subject: What do I need to change in order to do a complete settlement of an asset?

Hi,

For settling costs from project WBS element/Network activities, settlement
profile, Allocation structure/source structure are required. Maintain cost
elements used in project in allocation structure. PA transfer structure is
required to settle revenue in projects to profitability segment.

Please take CO consultant help, if required.

Regards

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2015 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
lokeshsethi  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language