Reply from sesh483 on Dec 28 at 1:06 PM Hi Settlement can be done 2 ways: A. If it is Asset Centric: capitalize from AUC to Final Asset: AIAB Create line item settlement Rules AIBU Settlement to Final Asset B. If it Project Centric Capitalize from projects to AUC then Final Assets CJ1C or KOB5 select specific line item for settlement CJ88/CJ8G or KO88/KO8G summary settlement. Seshu
| | | ---------------Original Message--------------- From: Nazmut Shahadat Khan Sent: Sunday, December 28, 2014 9:33 AM Subject: Partially Settlement of Order to Assets When i ve settled order to assets it gets partially. How i will do the total amount or remaining amount to assets. Please advice. Regards, Nazmut Shahadat Khan | | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |