Question from nhendell on Oct 2 at 9:50 AM Good morning, The following transactions were performed about 2 weeks ago: KZZ2, KP26 & CK40N (2015 cost only). I found that the target quantity on the process orders are higher than the planned quantity & the actual quantity for the components & labor hours. I don't know if the transactions affected the process orders or if it's something else. If it isn't the transactions, what would cause the target quantity to be almost double? Thank you, Nancy | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |