Reply from ashutosh-p on Oct 14 at 1:21 AM Hi, IN PO and PR Release Strategy can be set up to 8 level so ask your mm consultant to do it.
| | | ---------------Original Message--------------- From: jaiprakashsingh0123 Sent: Tuesday, October 14, 2014 12:28 AM Subject: Any Possibility to Change PO Release Strategy Into Three Steps Dear All, In our organisation, on Purchase order, PO release strategy is into 2 steps (like Purchase Head and Plant head). Now the requirement is, we are looking to change the same in to three steps (Like Purchase Head, Account Head, and Plant Head), while editing the same. Is there any possibility to do the same? If any setting is required, kindly let me know. Thanks and Regards, Jai | | Reply to this email to post your response. __.____._ | _.____.__ |