Question from USER_2286617 on Aug 27 at 3:28 PM
Hi All,

Could you please help to fix the below issue on project settlement.

We had a PO that was created with a wrong GL which did not allow us to
settle that WBS element. To correct this we reversed the GR's, corrected
the GL and re did all the GR's with the correct GL. However, we still
cannot settle that WBS since it used a wrong GL in the first place and we
have this issue every time. Once a WBS is created with a wrong GL it
doesn't allow us to settle the WBS even after the corrections.

SAP error message - KD503.


Kindly help to fix this problem.
 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2014 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
USER_2286617  
 
View this online
Ask a new question
 
In the Spotlight
Have a technical question? Need to find IT solutions? Ask your peers in the Toolbox for IT community.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language