We have added search box. Key in SAP issue keyword to search
TopBottom

Announcement: wanna exchange links? contact me at sapchatroom@gmail.com.

[sap-log-ps] Reservation not shown for Project Material

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Question from Hamed_Abedi on Jun 14 at 6:52 AM
We have entered some semi-finished materials under an activity in a project, but no reservation shown for them in MD04. For other finished materials, under the same activity, there is no problem.
Note: below Proc.Parameters are not set for semi-finished items, though we cannot change/set them in PS:

-Acct.assig.cat
-Special Stock
-Valuation
-Consumption

Can anyone please help with this issue?

Thanks,
 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2014 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
Hamed_Abedi  
 
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language