Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Reply from xiomaragarcia on Jun 11 at 12:16 PM Hi Maggie, Thanks for your reply. Order has CV scheduled line ( mov 601). The dn was assigned to a shipment and the shipment was completed and document cost generated and pay too. The problem is the good issue wasn't executed. I expected the system doesn't allow to make the shipment completion if the GI is still pending.
| | | ---------------Original Message--------------- From: Xiomara Garcia Sent: Wednesday, June 04, 2014 12:59 PM Subject: Where can i set as mandatory the GI, before shipment completion? For a delivery coming from sales order free charge, the shipment completion was allowed without good issue of the delivery. Where can I set GI as mandatory before the shipment completion? | | Reply to this email to post your response. __.____._ | _.____.__ |