Reply from robert greenberg on Jun 15 at 11:54 AM not possible. plaf planned order table records are by material
| | | ---------------Original Message--------------- From: ruhi yasmeen Sent: Sunday, June 15, 2014 6:50 AM Subject: One Planned Order for Multiple Materials hi friends, Is it possible to have one planned order for multiple materials. For ex:i want to rum MRP through MRP controller. MRP controller has been assigned for 10,10,10 material from 3 plants Plant 1 Plant 2 Plant 3. If i run MRP than planned order should generate plant wise. for one plant one planned order no mater how many materials are there but it should generate only one planned order with all these materials. Is this possible? please reply soon. | | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |