RE:[sap-log-pp] SAP Routing/BOM

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from KIRKUPM on Feb 10 at 10:06 AM
You probably already solved this problem but in the profile of the production order type auto goods receipt confirmation should be used to confirm the WIP into stock when the confirmation of the last operation is done.

---------------Original Message---------------
From: w t
Sent: Tuesday, October 15, 2013 3:31 PM
Subject: SAP Routing/BOM

We have multiple work orders which handle multiple processes, defined in the routing as sequence 10, 20, and 30.

In stage 1, at Sequence 10, raw materials are back flushed when CO11 (production confirmation) is done; this relieves RM inventory and records usage in the Cost Element; but the WIP inventory is not recorded in SAP.

Again in stage 1, at Sequence 20, CO11 is performed, WIP inventory is recorded in SAP, as this is the last step in the routing.

Currently, we have to manually accrue for the WIP inventory at month-end.

Looking for a feasible solution to have WIP inventory show up/recorded after Sequence 10 is confirmed.

Thanks,
WT

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2014 Ziff Davis, Inc. and message author.
Ziff Davis, Inc. 28 E 28th Street New York, NY 10016
KIRKUPM  

Consultant
achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language