Reply from DevidasKarad on Jan 3 at 4:24 AM Check your schedule margin key and its configuration
| | | ---------------Original Message--------------- From: Billie Sent: Friday, January 03, 2014 3:02 AM Subject: Scheduled Start Date Or Finished Date Changing in Process Order Hi PP Gurus, I am trying to find out the reason why the scheduled start date and finished date different from the Basic start date and finished date. Sometime the scheduled date is two or three days later than the basic finished date. How is the system calculating, maybe anyone of you can explain the concepts. This is impacting on the Capacity Evaluation that we are using. Hope to hear some explanation on this. Appreciate the assistance. Thanks & Regards BL | | Reply to this email to post your response. __.____._ | _.____.__ |