Reply from jim mcdowall on Jan 21 at 2:43 AM This is completely contradictory, you say that MRP views should not be created yet you want to know how to create an MRP type which resides in the MRP View on the material master. I am afraid you have no alternative. You will have to create the MRP view and then populate the MRP type. I cannot see how you will achieve your goal otherwise.
| | | ---------------Original Message--------------- From: Malin Sent: Monday, January 20, 2014 3:59 PM Subject: MARC-PRCTR Mass Update But Not MM17 vishvasvs, the whole problem is that MRP type is not even defined for these materials. MRP views are not created and should not be created. So there is no old to replace. | | Reply to this email to post your response. __.____._ | _.____.__ |