Question from DarekC on Nov 29 at 7:28 PM Hi Gurus, I hope you will help me with recycling/rework orders in make to stock scenario. My client wants to recycle very expensive components from scrapped finish good and also report amount of work (labour) which needs to be done for that purpose. Cost of labor should be posted in cost center responsible for recycling. What do you think how this scenario should be done in SAP? To indicate work (labor) we tried to use CO07 without material. we released production order only for labour time (work that needs to be done) but after confirmation when we tried to close production orders we faced problem. Those production orders cannot be closed because 'balance is not zero'. Hope i have expressed myself clearly thanks in advance | Reply to this email to post your response. __.____._ | _.____.__ |