Re: [sap-other] Cutover Strategy and Sequencing

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from sziaabbas on Mar 26 at 8:00 AM
Dear All

I see that most of you have not read my message properly, where I have
mentioned the modules that are being implemented. There is no cutover
strategy as of now and we are in the process of formulating that. That was
the reason I asked for your suggestions.

What basically I wanted to know is the sequencing of the activities that
one should follow?

---------------Original Message---------------
From: USER_1741894
Sent: Tuesday, March 26, 2013 6:10 AM
Subject: Cutover Strategy and Sequencing

Agreed. A draft cut-over plan is usually created at the beginbing of any DM project and is refined using data (timings , dependencies etc) from the test/simulation cycles. Usually the skeleton is put out by the PM then the functional consultants are expected to provide object dependencies , the DM lead is then expected to provide the object details E.G the steps required to load material master.Furqan Khan

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2013 Ziff Davis, Inc. and message author.
Ziff Davis, Inc. 28 E 28th Street New York, NY 10016
sziaabbas  

achievement
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have an SAP Question? Ask Your Peers at Toolbox for IT

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language