RE: [sap-other] Cutover Strategy and Sequencing

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from andyduk on Mar 26 at 3:11 AM
These are very fundamental questions, are you sure you are experienced enough to be in this role?

---------------Original Message---------------
From: srikrishna.durbha
Sent: Tuesday, March 26, 2013 2:55 AM
Subject: Cutover Strategy and Sequencing

Hi

Cutover strategy should go on the following lines for PS module for example:

1) How many projects must be uploaded, from which year on?

2) Do you need historical data (Actual costs, planned costs, etc)

3) What is the legacy system and how to extract existing data

4) How do you map legacy data to the new system (New project numbers,
WBS structures, Company code, Plant, cost center, etc)

5) Where do you maintain the mapping files and how the business would
validate and approve the mapping file

6) What is the method to convert the new data (from the mapping file)
to the SAP system (LSMW, BAPI, BDCs etc)

7) How many data conversion mock exercises are required before finally
uploading the same into the Live client

8) Trial balance

Hope this helps.

Regards
Srikrishna

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2013 Ziff Davis, Inc. and message author.
Ziff Davis, Inc. 28 E 28th Street New York, NY 10016
andyduk  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Toolbox.com for iPhone & Android: Ask Questions & Get Answers Anywhere. Download the Free App

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language