Reply from ha_tran on May 25 at 12:57 AM Hi, If you create your PR manually, then SAP won't consider the setting at the MRP Area level. Try to create your PR via MRP run and let me know how it goes. Cheers, HT
| | | ---------------Original Message--------------- From: VijayaSaravanan Sent: Thursday, May 24, 2012 5:59 AM Subject: Total Replenishment Lead Time in MRP 3 Hi Experts, I would like to know whether the total replenishment lead time could be maintained at the storage location as the delivery days from the central ware house differs from one storage location to other. Thanks in advance. Vijaya | | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |