Reply from BBMukherjee on Mar 3 at 8:31 AM Hi, Lead Time Calculation always takes place based on Experience and as in SAP there is no Vendor Calendar is exist we only depend upon Factory Calendar and calculation takes place based on that. If the Lead time is specifically used for your MRP Run, Schedule line created based on your Factory Calendar only, where there is no challenge for Production Loss if the Material is delivered as per Production schedule.
| | | ---------------Original Message--------------- From: Jeff Davis Sent: Friday, March 02, 2012 1:31 PM Subject: delivery lead times for vendor PO I am having the same issue and at the same time trying to solve for in transit times and shipping days from a vendor. Is that possible? | | Reply to this email to post your response. __.____._ | _.____.__ |