Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Reply from Jerry See on Mar 28 at 11:52 PM Hi Shahbaz, Check the procurement type of the costed material which should be "E". Then redo costing run for the said material. Regards, Jerry See
| | | ---------------Original Message--------------- From: saltaf Sent: Wednesday, March 28, 2012 11:24 AM Subject: Costed BOM is not Capturing Routing Hello I am looking at the Costed BOM window for an item, it shows the components but at the top in the routing column it does not show the routing and neither calulate the cost. Standard cost of the item does capture routing and component cost. When i click on the find bar beside routing it shows routing code "0". Please advise Shahbaz | | Reply to this email to post your response. __.____._ | _.____.__ |