We have added search box. Key in SAP issue keyword to search
TopBottom

Announcement: wanna exchange links? contact me at sapchatroom@gmail.com.

RE:[sap-log-mm] Process a Goods Receipt for material with Scheduling Agreement

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from mikepmoss on Jan 29 at 7:55 PM
In SA item details (ME32L) mark "Unlimited" checkbox next to overdelivery tolerance. This does have the disadvantage that GR is possible for any quantity, no matter how much you actually ordered. However, normally an SA is only created when you have a long standing relationship with the vendor so gross over-delivery should not happen.

---------------Original Message---------------
From: miguelalonso
Sent: Wednesday, June 18, 2008 10:30 AM
Subject: Process a Goods Receipt for material with Scheduling Agreement

Hi All,
I'm trying to process a goods reciept with Tcode MIGO_GR for a material that's under a Scheduling Agreement but i keep getting an alert that says" Document #of SA does not cantain any selectable items", any advice what i'm missing....i created the SA then the source list

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
mikepmoss  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have an SAP Question? Ask Your Peers at Toolbox for IT

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language