We have added search box. Key in SAP issue keyword to search
TopBottom

Announcement: wanna exchange links? contact me at sapchatroom@gmail.com.

RE:[sap-log-mm] MRP not to consider dependent requirements, but independent do.

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from ha_tran on Jan 9 at 7:04 PM
Hi Mark,

There are two options you can consider -

1) Create a separate storage location which is excluded from MRP run to stock your repairable items that are received through SO; or
2) Receive your repairable items and keep them in block stock status. Make sure that the related configuration to exclude block stock as part of current available stock shall be set.

Cheers,
HT

---------------Original Message---------------
From: MarkM
Sent: Monday, January 09, 2012 12:20 PM
Subject: MRP not to consider dependent requirements, but independent do.

How can i set for not considering dependend requirements in MRP and just take independent requirments? I have a lot of sales and production orders that are affecting my MRP result and purchasing quantities

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ha_tran  
Senior SAP Supply Chain Business Analyst
achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language