RE:[sap-log-mm] Cost Center Assigned on GR for PO with Account Assignment P - Project

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Posted by rms2010
on Sep 23 at 12:46 AM
Hi,

Thanks for your feedback.

However, how about the different cost center assignment between the PO items, while they are all assigned to the same WBS Element?

Furthermore I've checked on the WBS Element master data and found that no default cost center assigned to the WBS Element, nor to the Project Definition. And also settlement rule assignment is to Asset.

Is there anything that I miss to check?

Thanks

---------------Original Message---------------
From: Ha Tran
Sent: Thursday, September 22, 2011 6:25 PM
Subject: Cost Center Assigned on GR for PO with Account Assignment P - Project

Hi,

The cost center was assigned to your WBS element. However, the actual costs were allocated to your WBS element instead of cost center.

Cheers,
HT

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Popular White Papers

In the Spotlight
View the "Managing the Application Life Cycle" webinar and learn how organizations optimize their SAP applications.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language