We have added search box. Key in SAP issue keyword to search
TopBottom

Announcement: wanna exchange links? contact me at sapchatroom@gmail.com.

RE:[sap-acct] Availability check on internal orders

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Posted by JOMLV (Project Manager)
on May 23 at 6:48 PM
Mark this reply as helpfulMark as helpful
Thanks Allan, actually i checked the settings , budget profile was OK, detai lof order type, OKOB, KOAB ... although OK. Then i tested in the Quality system from a Purchase order in ME21, to add a good increase to the internal order and then i do get the error message. So As in Production, it seems that the message dooes not work and as the error message is set at 105% , because the test in production had an amount insufficuent to trigger the error message . i changed it to 100,2 % in the img and transported the change request to quality and Production. In quality , still working with a little amount : error message is triggered; but in production, in ME21 with an amount that is bigger than the 0,2 % i still don't have the error message triggered. Yet the custo is the same for the toleranace limits. KO30 in prod : availabilty check active . So i am going to recheck and compare everything beetwenn quality and Prod system . i also need to remove the purchase orde created
in Prod. I guess there is a tool to compare customizing tables across the landscape.


Jean





---------------Original Message---------------
From: JOMLV
Sent: Saturday, May 22, 2010 4:47 PM
Subject: Availability check on internal orders

> Dear All,
>
> I have an issue on availability check (AVAC) with internal orders. yet Committment management in CO is activated, as comittment in the order type. I also defined tolerance limits for AVC, for group all, ++, action 3 :error at 105 %.
> Then the internal order is budgeted by the users, but when they add purchase orders (committments) or make reception on that PO with an amount that is more than the budget, no message at all is raized.
> Everything sounds OK, in KO23 when analysing the AVAC log, all is active, operations from BS32, COIN ,RMBE, (commitmment : PO requets and Request) are done, but no operatin for Budget :RXPA.
> In order to replay the tests, do you know how to budget an internal order ? Is there additionnal customizing to do for AVAC, in MM on the Purchase Orders side maybe ?
>
> Jean,
__.____._
Copyright © 2010 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251

0 comments:

Post a Comment

T r a n s l a t e to your language