Re: Re: [sap-log-pp] MRP FOR MULTIPLE PLANTS

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Posted by 7250vinit
on Apr 22 at 3:18 AM
Mark this reply as helpfulMark as helpful
On Thu, 22 Apr 2010 05:37:47 +0530 wrote
>

dear sir,


You can use md01 for running mrp where u need to specify the planning scope this u can define using following tran code OM0E .here you can define a scope and in this acope you can define the sequence in which u need to run the mrp for diff plants.

check and revert.


vinit




Posted by Denise Michaels
> on Apr 21 at 8:10 PM


Mark as helpful





MD48 will give you visibility across plants.

>

>From: mrkriley via sap-log-pp

>To: Denise Michaels

>Sent: Wed, April 21, 2010 4:12:36 PM

>Subject: [sap-log-pp] MRP FOR MULTIPLE PLANTS

>

> Posted by mrkriley (Dir. Business Systems Dev)

>on Apr 21 at 7:13 PM

>

>We have 3 mfg plants and have some raw materials in each plant that can be used in all 3 plants. When we run the MRP list (MD06) we can enter only one plant at a time and see only the raws available and raw requirements in that particular plant.

>

>We?d like to be able to see the raw material stock and requirements in the other plants to see if we can transfer between plants as opposed to creating a PO and purchasing the raw.

>

>For example:

>MAT?L RAW01

>PLANT REQUIREMENT STOCK

>1000 100

>2000 200

>3000 300

>

>1000 120- 480

>2000 400 20

>

>If I ran MD06 for plant 1000 it would show I?m short by 20 kgs and create a purreq for it. However, I have 200 kgs in stock in plant 2000 that I can transfer from.

>

>Any help with this would be greatly appreciated.

>

>TX
__.____._
Copyright © 2010 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251

0 comments:

Post a Comment

T r a n s l a t e to your language