| | Posted by Denise Michaels on Mar 31 at 6:25 PM | |
Forecast based planning is not typically used with strategy 40. VV does not consider sales order requirements.
P* or M* MRP types are more common.
Note: simply changing the MRP type will not update the existing customer orders/deliveries as the demand type is based on the MRP setting at the time of the sales order entry, but new orders should have the correct demand type.
I provided a solution on how to update existing orders some time ago.
________________________________
From: SAP_OTC via sap-log-pp <sap-log-pp@Groups.ITtoolbox.com>
To: Denise Michaels <deniseemichaels@yahoo.com>
Sent: Wed, March 31, 2010 12:28:05 PM
Subject: [sap-log-pp] Stock Requirements List (MD04) and Available Qty. calculation
Posted by SAP_OTC (Credit Management)
on Mar 31 at 3:29 PM
When I go to MD04 there are two columns for each MRP Element, the "Rec./reqd.qty" and the "Available qty". For the Customer Requirements, "CusOrd" and/or "Delvry" nothing is displayed under the "Available qty" column.
Why is that?
For all other MRP Elements it does indicate if it's a Receipt or an Issue and it shows how that Receipt or Issue impacts the Available Qty.; but for the Sales Requirements it doesn't.
My Material has MRP Type VV Forecast Based Planning, it has Strategy 40 and this Strategy determines Requirement Type KSV with Requirement Class 050.
Is there anything I'm missing in the Requirement Class definition or maybe in my Material Master or should I be using a different Requirement Class and/or Requirement Type?
I would appreciate any ideas you may have for this to happen.
__.____._ P* or M* MRP types are more common.
Note: simply changing the MRP type will not update the existing customer orders/deliveries as the demand type is based on the MRP setting at the time of the sales order entry, but new orders should have the correct demand type.
I provided a solution on how to update existing orders some time ago.
________________________________
From: SAP_OTC via sap-log-pp <sap-log-pp@Groups.ITtoolbox.com>
To: Denise Michaels <deniseemichaels@yahoo.com>
Sent: Wed, March 31, 2010 12:28:05 PM
Subject: [sap-log-pp] Stock Requirements List (MD04) and Available Qty. calculation
Posted by SAP_OTC (Credit Management)
on Mar 31 at 3:29 PM
When I go to MD04 there are two columns for each MRP Element, the "Rec./reqd.qty" and the "Available qty". For the Customer Requirements, "CusOrd" and/or "Delvry" nothing is displayed under the "Available qty" column.
Why is that?
For all other MRP Elements it does indicate if it's a Receipt or an Issue and it shows how that Receipt or Issue impacts the Available Qty.; but for the Sales Requirements it doesn't.
My Material has MRP Type VV Forecast Based Planning, it has Strategy 40 and this Strategy determines Requirement Type KSV with Requirement Class 050.
Is there anything I'm missing in the Requirement Class definition or maybe in my Material Master or should I be using a different Requirement Class and/or Requirement Type?
I would appreciate any ideas you may have for this to happen.
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
SAP Logistics Production Planning Helper
Posted helpful replies on 5 threads in a group to earn a Bronze Achievement
In the Spotlight
55% of IT Pros Use Social Media to Advance Their Careers. See the Survey Results
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion