Re: [sap-log-mm] PR stays in MD04 afte conversion to PO

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Posted by kathleen_mcdowell
on Mar 8 at 11:17 AM
Mark this reply as helpfulMark as helpful
Are you sure you are not looking at MD06? If not, then make sure you
"refresh" MD04 after you have created the PO.

Just a couple of thoughts off the top of my head.

On Sat, Mar 6, 2010 at 4:47 AM, Joe Hines via sap-log-mm <
sap-log-mm@groups.ittoolbox.com> wrote:

> Posted by Joe Hines
> on Mar 6 at 11:05 AM
>
> MD04 is static. The planned order will remain until there until the next
> MRP run occurs.
>
> From: Liupukang via sap-log-mm [mailto:sap-log-mm@Groups.ITtoolbox.com]
> Sent: Friday, March 05, 2010 4:16 PM
> To: Hines, Joseph P
> Subject: [sap-log-mm] PR stays in MD04 afte conversion to PO
>
> [cid:image001.jpg@01CABD01.56C5EFF0]
>
> Posted by Liupukang
> on Mar 5 at 4:17 PM
>
> Hi, for a material with procurement type = 'X', when MRP runs, I see plan
> ord generated. After convert the pln ord to purchase req. and further
> convert it to PO, the PR stays in MD04. Anybody can help? Appreciat it.
__.____._
Copyright © 2010 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251

1 comments:

Anonymous said...

I just had the same problem. It turned out that PR was released for 4500kg, and then when converted to PO, the PO was changed to 2000kg. Thus when we refreshed MD04, the PR remained along with the PO, but the PR was for the remaining value that was released.

Post a Comment