Hi,
You are right that i can see the PR in production order itself.But can i see that PR at md04 also.
Thanks
sand324
On Tue, 02 Feb 2010 10:39:44 +0530 wrote
>



Posted by Ashok (SAP-PP and PS Consultant)
> on Feb 1 at 11:55 PM

Mark as helpful


Hi.
>
>You can see the purchase requisition in production order tab view CO 02 in
>operation view, select item details and view the purchase requisition number
>in purchase data tab.
>Still u have any queries please let me know.
>
> _____
>From: sand324 via sap-log-pp [mailto:sap-log-pp@Groups.ITtoolbox.com]
>Sent: 01 February, 2010 9:30 PM
>To: Ashok
>Subject: RE:[sap-log-pp] operation subcontracting
>
>
>
>
>Posted by sand324
>on Feb 1 at 11:35 AM
>
>Hi Ashok,
>The scenario is now working fine as i have put the procu. type X for sub con
>material(HALB) in material master but when Sub Con PR created after
>production order comes in picture for my halb material,I am not seeing that
>PR in MD04.I don't know why.
>sand324
>On Mon, 01 Feb 2010 11:39:31 +0530 wrote
>>
>
>Posted by Ashok (SAP-PP and PS Consultant)
>> on Feb 1 at 12:13 AM
>Mark as helpful
>
>Hi..
>>
>>Can you check the procurement key in MRP view material master? After MRP ,
>>purchase requisition will be created those materials which have procurement
>>key X or F and its depends on material type.
>>For external operation(subcontracting) maintain the PP02 control key in
>>Operation routings.
>>Pls.Check and revert back.
>>
>>Ashok
>>
>> _____
>>From: sand324 via sap-log-pp [mailto:sap-log-pp@Groups.ITtoolbox.com]
>>Sent: 01 February, 2010 5:59 AM
>>To: Ashok
>>Subject: [sap-log-pp] operation subcontracting
>>
>>
>>
>>
>>Posted by sand324
>>on Jan 31 at 8:10 PM
>>
>>PP Gurus,
>>I am fcing a problem in operation suncontracting scenario,
>>lets slearify,i hv two components B and C for a header material A.Component
>>C is a sub contracting material and B is in house one.
>>1-when i create the demand of A in MD61 and run the MRP ,autoamtic Planned
>>order create for A and B -that is ok.But i also get a PR of C (which is not
>>supposed to create)of same amount as i maintain in BOM of A.
>>2,When i convert the planned order of A into production order i can see a
>PR
>>is genenrated (with out material) upon saving of production order.
>>My query is that why PR is generated upon MRP run and when i save the
>>production order of A ,then why matarial(component C) is not coming in PR.
>>treat as urgent.
>>Thanks in advance
>>sand324
__.____._
Copyright © 2010 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251

0 comments:

Post a Comment

T r a n s l a t e to your language