Hi,

A couple of clarifications -

1) It is feasible that you can allow end user to manually create the the stock transfer requisition in ME51N transaction if MRP is not used in your case;
2) It is strongly recommended that you should not allow your end users to create the purchase requisition for the supplying plant as you won't be able to move your stock from supply plant to your receiving plant once the vendor delivers your shipment;
3) Lastly, SAP does not allow you to convert your purchase requisition for one plant into purchase order for another plant.

Cheers,
HT

---------------Original Message---------------
From: jarexx
Sent: Monday, January 25, 2010 1:25 PM
Subject: Multiple PReqs for a material to a single line on the PO

> Thanks Diane, I agree with the solution you proposed. However, I'm not running MRP so I'm considering customizing ME59N with a ZME59N that will consolidate the lines to a single plant. My reply to Santosh also says I'm considering giving PReq authorization to the lead plant to users at the ordering plants to negate the issue of separate plants creating the PReqs. Is customizing ME59N for this specific need possible?