[sap-log-pp] Fixed lot sizing and takt time

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Posted by doriangray(SAP PP (Production Planning) - Manager)
on 07/05/2009 02:08:00 PM

Hi! I'm using fixed lot size with backward overlapping for a material.I maintain a takt time of 5 days in the material master, and orders are created 5 days apart for this material via MRP.
I have an orders on15th, 20th and 25th. If for some reason the order on 20th is changed to 23th, then the next order must be be automatically shifted to 28th (since takt time is 5), and so on. How can this be done, without manually doing so?