[sap-log-pp] Best Practice For Setting Up Workcenters With Machines And Labor Resources.

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Question from AmericanBOA11 on Jun 30 at 10:58 AM
Within one cost center we have 7 manually operated machine resources, and 5 labor resources. A person must be available to operate any of the machines. Each machine will be assigned its own work center due machine specific products. We are looking for the following information.

Machine capacity

Labor capacity within the cost center or work center group.
 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
© 2017 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
AmericanBOA11  
 
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language