Reply from ABROO59 on Jun 21 at 3:51 AM u can do it with add a lock status for changing the quantity or new added component to PM order and assign a role for unblocking the order. until the order remaining in block status the movement is not allowed Your sincerely Akbar EBRAHINI ---
| | | ---------------Original Message--------------- From: Ha Tran Sent: Wednesday, June 20, 2012 7:59 PM Subject: PM Work Order Reservation Document Hi Mabelz, Unfortunately, this is the standard functionality of SAP i.e. you can add a new component to your PM work order after it is released. If you wish to prevent it (which is quite strange to me), then you should discuss in more details with your PM specialist to enhance the system. Cheers, HT | | Reply to this email to post your response. __.____._ | _.____.__ |